Track monitoring to RIL for safe rail infrastructure

During construction work next to and beneath tracks, we monitor track position, settlement and deformation to the standard of RIL 883.8100A01. With automatic data capture, remote transmission and proactive alerting.

Track monitoring on rail infrastructure with sensors and prism targets in the track area
Track geometry Online
  • Position nominal
  • Height nominal
  • Cant nominal
  • Twist nominal
RIL 883.8100A01

Why track monitoring

Why track monitoring is essential during construction work

Construction work near the track, temporary conditions and interventions in the subsoil can cause settlement, displacement and twist. Compliant geo-monitoring provides evidence and enables a fast response.

Request a quote

Construction near the track

Continuous recording of track geometry during construction states directly next to or beneath the track.

Drilling and piling works

Interventions in the subsoil cause settlement. The smallest changes in position are detected early.

Temporary bridges

Monitoring of position, cant and twist on temporary structures in the track area.

Switches and crossings

Geo-monitoring for tracks and switches to RIL requirements, even at sensitive junctions.

Traceability

Unbroken time series document the track condition before, during and after the construction phase.

Automatic alerting

If thresholds are reached, the system alerts immediately, around the clock and without an on-site check.

Measuring head at the edge of the track, with ballast bed and rails behind

RIL 883.8100A01

These are the parameters required by the guideline

RIL 883.8100A01, Deutsche Bahn’s guideline for track monitoring, defines minimum requirements for measurement and evaluation in geo-monitoring of tracks and switches. At least four parameters are monitored, and the scope can be extended as part of the risk assessment.

  1. 01

    Position

    Lateral position of the track, captured via measuring points on the sleeper grid.

  2. 02

    Height

    Vertical position of the rail, to reliably detect settlement and heave.

  3. 03

    Relative height (cant)

    Height difference between the two rails, decisive for running safety.

  4. 04

    Twist

    Change in cant over a defined length, a key safety criterion.

Measuring point density

Every 5 sleepers per rail, typically 3.00 m at a 60 cm spacing.

Measuring range

At least 25 m beyond the area of possible change.

Extendable

Gauge and absolute track geometry depending on the risk assessment.

Simulation

Detect settlement before it becomes critical

Subsoil interventions cause the track to sag. See how the height position is measured continuously and what happens once the defined threshold is reached.

Rail longitudinal profile, measuring points on the sleeper grid nominal
Threshold 3.0 mm Reference position (baseline measurement)

Demonstration only

Readings, measuring point M4

Continuous capture, 15 min cycle

mm
  • Position 0.0 ok
  • Height (settlement) 0.0 ok
  • Cant 0.0 ok
  • Twist 0.0 ok

Measurement technology

Total-station monitoring as the standard

For track monitoring to RIL requirements, high-precision total-station monitoring is the standard approach. Precise, automated and with continuous remote transmission.

Capture

Prism targets on the sleeper grid

Reflector targets are placed on the specified grid and automatically sighted by the motorised total station.

Evaluation

Automated measurement cycles

Defined measurement intervals deliver a robust evaluation of track geometry without manual intervention on site.

Operation

Remote transmission and alerting

All readings are transmitted securely and continuously checked against the defined thresholds. If a threshold is exceeded, alerting is triggered automatically.

Remote data transmission24/7 evaluationThreshold alarm

Automated total station monitoring

Automated total station monitoring of track: how the system works

A robotic total station measures the track from a fixed position, usually on an overhead line mast next to the track. It sights 360° prisms on the sleepers fully automatically, determines its own position in every cycle from reference prisms outside the zone of influence and derives position, height, cant and twist of both rails from the coordinates. The data reach the platform without anyone on site, where they are checked against the warning and alarm values of RIL 883.8100A01.

Robotic total station under a protective hood on a bracket on an overhead line mast next to the track, with a ladder for maintenance
Total station on a bracket on an overhead line mast, 2.50 to 3.00 m above ground.
Yellow 360° prisms on the sleeper ends along a track at night
Monitoring prisms on the sleepers, installed at night during a track possession.
σ ≤ ±3 mm
Accuracy for position, height and cant required by RIL 883.8100A01 up to 160 km/h
0.5″
Angle measurement accuracy of the total station (manufacturer specification)
0.6 mm + 1 ppm
Distance measurement accuracy to the prism (manufacturer specification)
≥ 4
Reference prisms per total station outside the zone of influence
≤ 1 h
Measuring cycle per total station, readings at least hourly

Accuracy

Millimetre accuracy, verified

RIL 883.8100A01 requires a standard deviation of ±3 mm for position, height and cant at line speeds up to 160 km/h. We work with robotic precision total stations with an angle measurement accuracy of 0.5″ and a distance accuracy of 0.6 mm + 1 ppm to the prism. Redundant observations, repeat and check measurements document the achieved measurement uncertainty.

Reference prisms

Stable reference outside the zone of influence

At least four reference prisms per total station sit outside the influence of excavations, jacking and open-cut work, before and behind the monitored track section, on overhead line masts or on neighbouring buildings. The mast carrying the instrument is not a reference point: the station position is recalculated from the reference prisms in every cycle.

Monitoring prisms

360° prisms every five sleepers

The monitoring prisms sit on the outside of the sleeper ends, every five sleepers on each rail, around every 3 m. Because both rails are measured, cant and twist follow directly from the readings. Installation takes place at night during a track possession. Spare prisms are kept in stock; a damaged prism is replaced in the next possession and taught in again.

Temperature compensation

Temperature and air pressure measured at the station

Air temperature and air pressure change how the measuring beam travels, and the mast itself moves in the daily temperature cycle. Temperature and air pressure sensors at the station therefore measure continuously. These values are used to apply an atmospheric correction to every distance measurement, and the station position determination from the reference prisms also captures any movement of the mast. What remains is the movement of the track.

Data transfer and power

Mobile network, mains or self-sufficient

After each cycle, the station sends the readings securely over the mobile network to the evaluation server, where they are stored and available in real time on the online portal. Power comes from a fixed connection where one is available; otherwise the station runs self-sufficiently on solar modules and buffer batteries.

Evaluation

Position, height, cant, twist

Every cycle is compared with the baseline measurement, which runs over several cycles before construction starts. The platform calculates position, height, relative height (cant) and twist and checks them against the warning and alarm values. Automated routines check every time series for completeness and plausibility and flag jumps and outliers.

Alerts

Warning value and alarm value

Following RIL, there are two levels: the warning value and the alarm value as the threshold for immediate intervention. Alerts go by email, and by SMS on request, to the group of people named in the alarm plan of the client. If a station fails, the system reports that too, so that no gap in monitoring goes unnoticed.

Remote operation

Operated and maintained remotely

Operating status, communication and power supply of each total station are monitored continuously. Measuring programmes and intervals can be adjusted remotely. On site, we service the stations every six months and as required. Reports: baseline report, weekly regular reports and a final report, with monitoring continuing for at least two weeks after the works end.

Warning and alarm values by line speed

Values as specified in RIL 883.8100A01, tables 1 to 3, as used in our measuring programmes. DB can adjust them after the baseline measurement.

Line speedPosition and heightRelative height (cant)Twist
80 km/h12 / 21 mm10 / 15 mm3.5 / 6.0 ‰
≤ 120 km/h10 / 17 mm8 / 13 mm3.5 / 6.0 ‰
≤ 160 km/h8 / 14 mm7 / 11 mm3.5 / 6.0 ‰

Warning value / alarm value

Infrasolute platform

All readings on the Infrasolute platform

The sensors transmit their readings to the platform. There they are continuously checked against your limit values, evaluated with AI and documented, accessible in the browser around the clock.

Platform modules

The platform at a glance
Bridge as a 3D model on the Infrasolute platform, measuring points coloured by status
Sample view

A monitoring concept for your construction project at the track

Tell us about your project in the track area. We will propose an RIL-compliant monitoring concept and get back to you shortly with a no-obligation quote.

Roman Koch Roman Koch

Applications

Where track monitoring shows its strength

Wherever construction work can affect track geometry, continuous geo-monitoring provides safety and traceability.

For rail

Monitoring for rail operators, train operating companies and engineering offices

Whether a construction firm, an operator or a planning office: we combine track monitoring and RIL expertise for everyone involved in the rail environment.

FAQ

Frequently asked questions about track monitoring

Which parameters must be monitored as a minimum?
RIL 883.8100A01 requires at least position, height, relative height (cant) and twist. Extensions such as gauge or absolute track geometry are defined on a project-specific basis through the risk assessment.
At what spacing are measuring points placed?
Measuring points are placed at intervals of five sleepers per rail. With a sleeper spacing of 60 cm, this typically results in a grid of 3.00 m.
How large does the measuring range need to be?
The measuring range extends at least 25 m beyond the area of possible change and is extended on a project-specific basis so that edge zones are also reliably captured.
Why is total-station monitoring the standard?
Total-station monitoring enables high-precision, automated capture of track geometry via prism targets on the RIL grid. This makes it ideally suited to continuous monitoring and automatic alerting.
How accurate is automated total station monitoring of track?
RIL 883.8100A01 requires a standard deviation of ±3 mm for position, height and cant at line speeds up to 160 km/h. Our robotic precision total stations measure angles to 0.5″ and distances to 0.6 mm + 1 ppm to the prism (manufacturer specifications). Redundant observations, repeat and check measurements document the measurement uncertainty achieved in the project.
What are the reference prisms for?
At least four reference prisms per total station sit outside the zone of influence of the works, before and behind the monitored section, on overhead line masts or neighbouring buildings. The total station uses them to redetermine its own position in every cycle. If the mast it stands on moves, this is detected and corrected.
How is the influence of temperature compensated?
Temperature and air pressure sensors at the station measure continuously. Their values are used to apply an atmospheric correction to every distance measurement, because air temperature and air pressure change how the measuring beam travels. The daily temperature cycle also moves the mast. This is captured by the station position determination from the reference prisms in every cycle. What remains is the movement of the track.
How is the total station powered, and how do the data reach the portal?
Where a fixed power connection is available, it is used; otherwise the station runs self-sufficiently on solar modules and buffer batteries. After each cycle, the readings are sent securely over the mobile network to the evaluation server and are available in real time on the online portal. Operating status, communication and power supply are monitored continuously.
When is additional gauge monitoring required?
Additional gauge monitoring is required when the risk assessment demands it, for example with special structures such as bridges with individual support points.
Does Infrasolute also take care of ongoing operation?
Yes. From concept through installation to ongoing operation, you get everything from a single source. On request, we can take over monitoring completely as an outsourced department, including evaluation and alerting.

Project inquiry

A monitoring concept for your construction project at the track

Tell us about your project in the track area. We will propose an RIL-compliant monitoring concept and get back to you shortly with a no-obligation quote.

[email protected]
Project inquiry